Analisis De Insumos En Ad
|
| | | | | | | |
PARTIDA: | 01.01.00 | ALMACEN OFICINA Y CASETA DE GUARDIANIA | |
METRADO: | 0.50 | | | | UNIDAD: | GLB | |
INSUMOS | UND | CANTIDAD | TOTAL | |
MANO DE OBRA | | | | | | |
| OFICIAL | HH | 1.3333 | 0.67 | |
| PEON | HH | 2.6667 | 1.33| |
| | | | | |
MATERIALES | | | | | | |
| ALAMBRE NEGRO RECOCIDO Nº 8 | KG | 7.5000 | 3.75 | |
| CEMENTO PORTLAND TIPO IP | BOL | 1.5000 | 0.75 | |
| HORMIGON | M3 | 0.6000 | 0.30 | |
| MADERA NACIONAL P/ENCOFRADO | P2 | 120.0000 | 60.00 | |
| | | | | |
EQUIPO | | | | | | |
| HERRAMIENTAS MANUALES | %MO | 2.0000 | 0.01 | | | | | | | |
| | | | | | | |
PARTIDA: | 01.02.00 | CARTEL DE IDENTIFICACION DE OBRA | |
METRADO: | 1.00 | | | | UNIDAD: | GLB | |
INSUMOS | UND | CANTIDAD | TOTAL | |
MATERIALES | | | | | | |
| CARTEL DE OBRA | GLB | 1.0000 | 1.00 | |
| | | | | |
| | | | | | | |
PARTIDA: | 02.01.00 | TRAZO, NIVELES Y REPLANTEO DURANTE LAOBRA | |
METRADO: | 0.50 | | | | UNIDAD: | M2 | |
INSUMOS | UND | CANTIDAD | TOTAL | |
MANO DE OBRA | | | | | | |
| TOPOGRAFO | HH | 0.0800 | 0.04 | |
| PEON | HH | 0.2400 | 0.12 | |
| | | | | |
MATERIALES | | | | | | |
| YESO EN BOSLAS DE 25 KG | BOL | 0.0500 | 0.03 | |
| MADERA NACIONAL P/ENCOFRADO | P2 | 0.0200 | 0.01 | |
| | | | | |
EQUIPO | | | | | | |
| HERRAMIENTAS MANUALES | %MO | 3.0000 | 1.50 | |
| WINCHA DE 50 M | HE | 0.0800 | 0.04 | |
| | | | | |
| | | | | | | |
PARTIDA: | 02.02.00 | CERCO PROVISIONAL | |
METRADO: | 0.50 | | | | UNIDAD: | M | |
INSUMOS | UND | CANTIDAD | TOTAL | |
MANO DE OBRA | | | | | | |
| OPERARIO | HH | 0.1600| 0.08 | |
| OFICIAL | HH | 0.1600 | 0.08 | |
| PEON | HH | 0.1600 | 0.08 | |
| | | | | |
MATERIALES | | | | | | |
| CLAVOS PARA MADERA C/C | KG | 0.0500 | 0.03 | |
| PALO DE EUCALIPTO DE 3" | UND | 1.0000 | 0.50 | |
| MALLA ARPILLERA | M | 2.4000 | 1.20 | |
| | | | | |
EQUIPO | | | | | | |
| HERRAMIENTAS MANUALES | %MO| 3.0000 | 1.50 | |
| | | | | |
| | | | | | | |
PARTIDA: | 02.03.00 | AGUA PARA LA CONSTRUCCION | |
METRADO: | 1.00 | | | | UNIDAD: | MES | |
INSUMOS | UND | CANTIDAD | TOTAL | |
MATERIALES | | | | | | |
| AGUA P/OBRA | MES | 1.0000 | 1.00 | |
| | | | | |
| | | | | | | |
PARTIDA: | 02.04.00 | ENERGIA PARA LA CONSTRUCCION| |
METRADO: | 1.00 | | | | UNIDAD: | MES | |
INSUMOS | UND | CANTIDAD | TOTAL | |
MATERIALES | | | | | | |
| ENERGIA ELECTRICA P/OBRA | MES | 1.0000 | 1.00 | |
| | | | | |
| | | | | | | |
PARTIDA: | 02.05.00 | LIMPIEZA DE TERRENO MANUAL | |
METRADO: | 0.50 | | | | UNIDAD: | M2 | |
INSUMOS | UND | CANTIDAD | TOTAL | |
MANO DE OBRA || | | | | |
| PEON | HH | 0.6400 | 0.32 | |
| | | | | |
EQUIPO | | | | | | |
| HERRAMIENTAS MANUALES | %MO | 3.0000 | 1.50 | |
| | | | | |
| | | | | | | |
PARTIDA: | 02.06.00 | DEMOLICION DE PISO EXISTENTE | |
METRADO: | 0.50 | | | | UNIDAD: | M2 | |
INSUMOS | UND | CANTIDAD | TOTAL | |
MANO DE OBRA | | | | | ||
| PEON | HH | 0.8000 | 0.40 | |
| | | | | |
EQUIPO | | | | | | |
| HERRAMIENTAS MANUALES | %MO | 3.0000 | 1.50 | |
| | | | | |
| | | | | | | |
PARTIDA: | 02.07.00 | ELIMINACION DE DESMONTE CON VOLQUETE 4 M3 | |
METRADO: | 0.50 | | | | UNIDAD: | M3 | |
INSUMOS | UND | CANTIDAD | TOTAL | |
MANO DE OBRA | | | | | | |...