CONCEPTO | Un. | Gpo. | RENDIMIENTO APRXIMADO POR GRUPO | COSTO UNITARIO DEL TRABAJO TIPO A TIPO B |
CASTILLOS Y CADENAS 15 X 15 CON 4 (3/8´´) 9.5 MM. | M | 5 | 10 M/JOR | 34.59 | 24.18 |
CASTILLO Y CADENAS 15 X 20 CON 4 (3/8´´) 9.5 MM. | M | 5 | 9.5 /MJOR | 36.41 | 25.45 |
CASTILLO Y CADENAS 15 X 30 CON 4 (3/8´´) 9.5 MM. | M | 5 | 8 M/JOR | 43.23 | 30.22 |SOBRE PRECIO CARA APARENTE CASTILLOS Y CADENAS | M | 5 | 25 M/JR | 13.83 | 9.67 |
RECUBRIMIENTOS.- |   |   |   |   |   |
REPELLADOS DE MEZCLA | M2 | 5 | 19 M2/JOR | 18.2 | 12.72 |
APLANADOS DE MEZCLA | M2 | 5 | 14M2/JOR | 24.7 | 17.27 |
APLANADOS DE MEZCLA (ROSTREADOS) | M2 | 5 | 11 M2/JOR | 31.44 | 21.98 |
APLANAD0S FINOS DE MEZCLA | M2 | 5 | 10 M2/JOR | 34.59 | 24.18 |
APLANADOSPULIDOS DE CEMENTO A LLANA | M2 | 5 | 23 M2/JOR | 15.04 | 10.51 |
CONFITILL SOBRE APLANADOS | M2 | 6 | 4 M2/JOR | 90.97 | 63.63 |
RECUBRIMIENTO CINTILLA 5.5X22X1.0 A 6.0X24X1.0CM. | M2 | 6 | 4.5 M2/JOR | 80.86 | 56.56 |
RECUBRIMIENTO FACHALETA 10X20X1 A 11X22X1CM. | M2 | 6 | 5 M2/JOR | 72.78 | 50.9 |
RECUBRIMIENTO AZULEJO | M2 | 6 | 5.5 M2/JOR | 66.16 | 46.27 |
RECUBRIMIENTO TIP VITRICTA6X20X18CM | M2 | 6 | 4.5 M2/JOR | 80.86 | 56.56 |
RECUBRIMIENTO TIP VITRICTA 10X20X1.8CM | M2 | 6 | 5 M2/JOR | 72.78 | 50.9 |
RECUBRIMIENTO MOSAICO 20X20X2.0CM | M2 | 5 | 9 M2/JOR | 38.43 | 26.86 |
BOQUILLA INCLUYANDO CORTES A 450 MATERIAL VERIFIACADOS | M2 | 6 | 16 M/JOR | 27.74 | 15.91 |
SOBRE PRECIO POR TENIDOS EN FACHADAS | M2 | 3 | 43 M2/JOR | 8.08 | 5.72 |
  |   |   |   |   |   |PISOS.- |   |   |   |   |   |
FIRMES DE CONCRETO PARA PISOS, ESPESR DE 8 A 10 CM | M2 | 2 | 10 M2/JOR | 19.38 | 13.41 |
ACABADO ESCOBILLADO INTEGRAL SOBRE FIRMES | M2 | 5 | 35 M2/JOR | 9.88 | 6.91 |
FINO NO INTEGRAL ACABADO PULIDO | M2 | 5 | 18 M2/JOR | 19.21 | 13.43 |
ARMADO CON MALLA EN PISOS | M2 | 4 | 50 M2/JOR | 5.13 | 3.63 |
PISOS CERAMICA SIN FIRME | M2 | 6 | 5 M2/JOR | 72.78| 50.9 |
PISOS LOSETA 15X15X1.0CM A 2CM | M2 | 6 | 7 M2/JOR | 51.98 | 36.36 |
PISOS LOSETA 10X20X1.0 A 2.0CM | M2 | 6 | 7 M2/JOR | 51.98 | 36.36 |
PISOS LOSETA 30X30X2.5CM | M2 | 6 | 13 M2/JOR | 27.99 | 19.58 |
PISOS MOSAICO 20X20X2CM | M2 | 5 | 11 M2/JOR | 31.44 | 21.98 |
PISOS MOSAICO TERRAZO SIN JUNTA METALICA 50X50X2.5CM | M2 | 6 | 9.5 M2/JOR | 38.3 | 26.79 |
ZOCLO MOSAICO10X20X2.0CM | M | 6 | 18 M/JOR | 20.22 | 14.14 |
ZOCLO LOSETA 10X15X30 A 40CM | M | 6 | 18 M/JOR | 20.22 | 14.14 |
  |   |   |   |   |   |
MARTELINADOS.- |   |   |   |   |   |
MARTELINADO FINO SOBRE PISOS | M2 | 1 | 4 M2/JOR | 39.96 | 27.53 |
MARTELINADO FINO SOBRE COLUMNAS | M2 | 1 | 2 M2/JOR | 79.93 | 55.07 |
MARTELINADO FINO SOBRE MUROS | M2 | 1 | 3 M2/JOR | 53.29 | 36.71 |MARTELINADO FINO SOBRE TRABES Y LOSAS | M2 | 1 | 2 M2/JOR | 79.23 | 55.07 |
  |   |   |   |   |   |
AZOTEAS.- |   |   |   |   |   |
RELLENOS DE TEZONTLE EN AZOTEAS | M3 | 1 | 2 M3/JOR | 79.93 | 55.85 |
ENTORTADO SOBRE CASCO | M2 | 5 | 20 M2/JOR | 17.29 | 12.09 |
ENLADRILLADO Y ESCOBILLADO | M2 | 5 | 11 M2/JOR | 31.44 | 21.98 |
ENLADRILLADO APARENTE | M2 | 5 | 7 M2/JOR | 49.41 | 34.54 |CHANFLANES PEDACERIA | M2 | 5 | 24 M/JOR | 14.41 | 10.07 |
VARIOS.- |   |   |   |   |   |
HECHURA DE TARIMAS 50X100CM | PZA. | 3 | 19 PZA/JOR | 18.3 | 12.95 |
MURO BLOCK VIDRIO 10X20X20CM INCLUYENDO REFUERZO EN JUNTAS | M2 | 6 | 3.5 M2/JOR | 103.97 | 72.71 |
REGISTRO DE 40X60CM CON PROFUNDIDAD PROMEDIO 1.25 M | PZA. | 5 | 2 PZA/JOR | 172.93 | 120.88 |
TAPA DE REGISTRO DE 40X60CM | PZA. | 5 | 6PZA/JOR | 57.64 | 40.29 |
IMPERMEABILIZACION DE CIMIENTOS | M | 2 | 35 M/JOR | 5.54 | 3.83 |
ALBAÑILES 15 CM TENIENDO Y JUNTE | M | 5 | 26 M/JOR | 13.3 | 9.3 |
CLOCACION DE HERRERIA | M2 | 5 | 7.5 M2/JOR | 46.12 | 32.23 |
IMPERMEABILIZACION AZTEA POR CAPA | M2 | 2 | 30 M2/JOR | 6.46 | 4.47 |
| | | | | |
PRELIMINARES Y CIMENTACION.- |   |   |   |   |   |
LIMPIA Y TRAZ | M2...