Smed Implementation
FAU-I-PSG-5005
SMED Implementation Guide
PURPOSE SCOPE
All
This guide provides production managers and SMED coordinators with a methodological tool for the organization andmonitoring of a SMED workshop.
Faurecia production related activities.
RELATED DOCUMENTS • Receive and Maintain Tooling and Equipment FAU-P-PSC-6840
• Tool changeover tracking FAU-F-PSG-5005Issue
02
Date
Sept.. 2007
Description of changes
New document reference and cover page added for FCP
Cancels or replaces
FAU-S-PS-5005/EN issue 1
Author Verified by Owner
PC & L P.Bikard Alain Prioul, Group Production System VP
Approved by Alain Prioul, Group Production System VP
Please check that you have the latest version of this document. Internal. Property of Faurecia1/28
FAU-I-PSG-5005/EN Issue 02 –Sept. 2007
Production
CONTENTS
Introduction..................……………………...……........………… 3 Definition...................………………………………….……......… 4
SMEDWORKSHOP PROCEDURE
1 - Observe..............................……......………………...…........ 5 2 - Organize..................................………………...................… 7 3 - Setup............................................………...........….....….… 10 4 - Improve....................…………...........…………...........…...... 11 5 - Standardize.............………...............…......……….......….... 13
SMEDWORKSHOP ORGANIZATION
—SMED planning...........………..……………….…...…......…....14 —Workshop action .............…………...............………….......... 17
Please check that you have the latest version of thisdocument. Internal. Property of Faurecia
2/28
FAU-I-PSG-5005/EN Issue 02 –Sept. 2007
Production
INTRODUCTION
Just-In-Time production (JIT) means producing the quantity and qualitydemanded by the customer, with the lowest possible level of stocks or works in progress (WIP) and consuming only the resources which are strictly necessary. In case of a diversified demand, this can be...