I MOVIMIENTO TIERRA.
1,3EXCAVACIONES.
|ITEM |UNIDAD |CANTIDAD |P. UNITARIO |P. TOTAL |
|I MOVIMIENTO DE TIERRA | | | | |
|RETRO EXCAVADORA |HORA |0,12 |9500|1.140 |
|CAMION 3/4 |HORA |0,038 |1500 |57 |
|CAPATAZ |DIA |0,05 |16000 |800 |
|JORNALERO |DIA |0,1 |7500 |750 ||D. HERRAMIENTA |% |10 |----- |75 |
|LEYES SOCIALES |% |40 |---- |620 |
|GASTOS GENERALES |% |20 |---- |677 |
|| | |TOTAL |$ 4.119 |
2 RELLENO ZANJAS.
|ITEM |UNIDAD |CANTIDAD |P. UNITARIO |P. TOTAL |
|RELLENO ZANJA. | | | ||
|BULLDOZER |HORA |0,007 |40000 |280 |
|RODILLO COMPACTADOR |HORA |0,025 |20000 |500 |
|CAMION AGUA ALGIBE |HORA |0,007|6800 |48 |
|JORNALERO |DIA |0,1 |8500 |850 |
|LEYES SOCIALES |% |40 | |340 |
| | | |TOTAL |$ 2018 |
II TRANSPORTE, COLOCACION Y PRUEBA DE CAÑERIAS Y P. ESPECIALES.
4TRANSPORTE DE CAÑERIAS DE PVC, TIPO AP, CLASE 10.
|ITEM |UNIDAD |CANTIDAD |P. UNITARIO |P. TOTAL |
|TRANSPORTE DE CAÑERIAS, PVC,C10 | | | | |
|TRANSPORTE (CAMIONETA) |KG |1 |204 |204 |
|JORNALERO |DIA |0,02 |8500|170 |
|LEYES SOCIALES |% |40 |---- |68 |
| | | |TOTAL |$ 442 |
5 TRANSPORTE DE PIEZAS ESPECIALES DE PVC.
|ITEM|UNIDAD |CANTIDAD |P. UNITARIO |P. TOTAL |
|TRANSPORTE DE PIEZAS ESPECIALES DE PVC | | | | |
|TRANSPORTE (CAMIONETA) |KG |1 |436 |436...