Basicos deobra
Material | Unidad | Cantidad | Precio unitario | Importe |
Cemento | ton | 0.286 | $1,724.00 | $493.06 |
Arena | m3 | 0.500 |$125.00 | $62.50 |
Grava | m3 | 0.680 | $216.00 | $146.88 |
| | | Subtotal | $702.44 m3 |
Básicos de Concreto | F'c= 150 kg /cm2 | Castillos y Dalas |
Material | Unidad | Cantidad | Preciounitario | Importe |
Cemento | ton | 0.354 | $1,724.00 | $610.29 |
Arena | m3 | 0.480 | $125.00 | $60.00 |
Grava | m3 | 0.670 | $216.00 | $144.72 |
| | | Subtotal | $815.01 m3 |
Básicosde Concreto | F'c 200 kg /cm2 | Losas y Trabes |
Material | Unidad | Cantidad | Precio unitario | Importe |
Cemento | ton | 0.391 | $1,724.00 | $674.08 |
Arena | m3 | 0.470 | $125.00 | $58.75|
Grava | m3 | 0.650 | $216.00 | $140.40 |
| | | Subtotal | $873.23 m3 |
Básicos de Mortero | Cemento-Arena 1:5 | Muros Aplanados |
Material | Unidad | Cantidad | Precio unitario |Importe |
Cemento | ton | 0.380 | $1,724.00 | $655.12 |
Arena | m3 | 1.150 | $125.00 | $143.75 |
| | | Subtotal | $798.87 m3 |
Cuadrillas | Integrantes | Precio unitario | Fasar | Jornada |Total |
C01 | Ayudante | $200.00 | 60% | 1 | $320.00 |
| Cabo vigilancia | $350.00 | 60% | 0.05 | $28.00 |
| | | | Subtotal | $348.00 |
C02 | Oficial albañil | $320.00 | 60% | 1 |$512.00 |
| Ayudante | $200.00 | 60% | 1 | $320.00 |
| Cabo vigilancia | $350.00 | 60% | 0.05 | $28.00 |
| | | | Subtotal | $860.00 |
Limpieza
Material/M.O. | Unidad |Cantidad | Precio Unitario | Importe |
C01 | J | 0.125 | $348.00 | $4.35 |
| | Rendimiento | H. menor | |
| | 80 m2= 0.125 | 3% M.O. | $0.13 |
| Costo directo | Costo indirecto | Subtotal |$4.35 |
| $4.35 | 25% | Total | $5.60 |
Excavación
Material/M.O. | Unidad | Cantidad | Precio Unitario | Importe |
C01 | J | 0.33 | $348.00 | $115.88 |
| | Rendimiento | H. menor | |...