Calculo dalas de cerramiento

Páginas: 8 (1858 palabras) Publicado: 15 de diciembre de 2010
Dalas de cerramiento

Volumen de dala de cerramiento:
V = (0.28m) (0.20m) (3.28m) = 0.1837m3
Volumen de Varilla #3 (3/8”):
V= π (3/16 x 0.0254m)2(3.28m)(6)=0.0014m3
Volumen de estribos #2 (1/4”):
l = 2(0.24m) + 2(0.16m) + 0.1m = 0.9m
V= π (1/8 x 0.0254m)2(0.9m)(17)=0.00048m3
Longitud de alambre recocido:
L = 17 (6) (0.2m) = 20.4m
Volumen de concreto:V=0.1837m3-(0.0014m3+0.00048m3)= 0.1818m3
Proporcionamiento:
F´c = 200kg/cm2
TMA = 3/4”
Cemento = 1 saco = 30lts
Agua = 1.5 b = 27lts
Arena = 4 b = 72lts
Grava = 5 b = 90lts
Total = 219lts

Volumen efectivo de concreto:

f´crKg/cm2 | r=2.45 |
| 19 mm | 38 mm |
200 | 175 | 195 |

F = 175lts/219lts = 0.7991
Volumen total de materiales por separado:
V = 0.1818 m3/0.7991 = 0.227m3
Cemento:
0.03----0.219m3X------0.227m3 X = 0.0311 ≈ 1.036 sacos

Agua: 27lts * 1.036 = 27.97lts
Arena: 0.072m3 * 1.036 = 0.075m3
Grava: 0.072m3 * 0.746 = 0.0537m3

Peso de varilla #3:
W= 0.0014m3 (7850 kg/m3) = 10.99kg
Peso de varilla #2:
W = 0.00048m3 (7850 kg/m3) = 3.768kg
Peso del alambre recocido:
W = 20.4m (0.015625 kg/m) = 0.3187kg

Material | Unidad | Cantidad de un castillo | 10% dedesperdicio | $ Precio | $ Importe |
Cemento | Sacos | 1.036 | 1.1396 | 110 | 125.356 |
Arena | m3 | 0.075 | 0.0825 | 125 | 10.3125 |
Agua | lts | 27.97 | 30.767 | - | - |
Grava | m3 | 0.093 | 0.1023 | 150 | 15.345 |
Varilla #3 | Kg | 10.99 | 12.089 | 9.50 | 114.845 |
Varilla #2 | Kg | 3.768 | 4.1448 | 13 | 53.8824 |
Alambre recocido | Kg | 0.3187 | 0.3506 | 13.50 | 4.7331 |Total de importe = 324.474

Grupo de trabajo 5
Salarios Diarios
1 Oficial Albañil = $125.00
1 peón = $105.00
FSR = 1.33
PRE = 27%
Oficial Albañil
SDR =$125.00+$125.000.271.33 = $211.14
Peón
SDR=$105.00+$105.000.271..3 =$177.36
Salario Diario Real Cuadrilla
SDR = $388.50
2.- Costo de mano de obra
* Armado de Acero de Refuerzo
WT= 16.5844 kg = 0.01658ton
Rend= 0.15 tonJTiempo de Armado de Acero de Refuerzo
1J----→0.15 ton
t----→0.01658ton t=0.1105J
Costo de Armado de Acero de Refuerzo
Costo = $388.50 (0.1105J) = $42.93
* Cimbra
A= 0.23.282=1.312 m2
Rend= 9m2J
Tiempo de Cimbra
1J----→9m2
t----→ 1.312 m2 t=0.1457J
Costo de Cimbra
Costo = $388.50 (0.1457J) = $56.33
* Hechura de Cimbra
A= 0.23.282=1.312 m2
Rend= 10m2J
Tiempo Hechura deCimbra
1J----→10m2
t----→ 1.312m2 t=0.1312J
Costo de Hechura de Cimbra
Costo = $388.50 (0.1312J) = $50.97
* Colado del Concreto
v=0.1837m3
Rend= 0.95m3J
Tiempo de Colado del Concreto
1J----→0.95m3
t----→0.1837m3 t=0.1933J
Costo de Colado del Concreto
Costo = $388.50 (0.1933J) = $75.097
Costo de Mano de Obra |
Actividad | Importe |
Armado de Acero de Refuerzo | $42.93|
Cimbra | $56.33 |
Hechura de Cimbra | $50.97 |
Colado del concreto | $75.097 |
MO = $225.327 |

* Mandos intermedios (7%)
MI=0.07$225.327=$15.77
* Costo de herramienta (3%)
Costo =0.03$225.327= $6.7598
* Curado
Costo =$32.00/m2(0.9184)= $29.389
* Cimbra
Costo =0.9184$28.00= $25.715
Costos Directos = $324.474+ $225.327+ $15.77+ $6.7598+ $29.389+ $25.715=627.43
020.200 = to = (0.258) = 46.7
* Utilidad (10%)
Utilidad=0.1627.43 =$62.743
Precio Unitario |
Concepto | Importe |
Materiales | $324.474 |
Mano de Obra | $225.327 |
Herramienta | $6.7598 |
Mandos Intermedios | $15.77 |
Curado | $29.389 |
Cimbra | $25.715 |
Utilidad | $62.743 |
Total = $690.178 |

Dala de cerramiento para muro de 15 cm

Volumen dala de cerramientoV=(.15)(.36)(3.17)
V= 0.1427m3
Volumen varilla #3
V=π316*0.025428(3.17)
V=0.00181m3
Volumen estribos #2
L= 2(0.26)+2(0.11)+0.1
L=.84
V=π18*0.025420.84(17)
V= 0.000452m2
Longitud alambre recocido
L= 17(.20)(8)
L= 27.2

Volumen de concreto
V=0.1427-(0.00181+ .000452)
V= 0.1404m3
Proporcionamiento
f’c= 200 kg/cm2
T.M.A 34
Cemento = 1saco = 30 lts.
Agua =...
Leer documento completo

Regístrate para leer el documento completo.

Estos documentos también te pueden resultar útiles