BUILDING SYSTEMS COMMISSIONING CHECKLIST
The following list provides potential systems that could require commissioning.
1.0 AIR DISTRIBUTION:
The Commissioning Agent(CA) will verify and report on the operation and accessibility of the following items.
1.1 EQUIPMENT:
____ Air filtration, dampers, diffusers, grilles, fire dampers and access doors.
____ Hoodsand exhaust systems.
____ Heat buildup or noise in motor or shaft bearings.
____ Humidification equipment.
1.2 BALANCING:
Perform balancing for the following devices:
____ Motorcurrent draw. Compare running current to nameplate full load amps rating.
____ Motor starter contactor size and overload heater size.
____ Voltage and rotation of each motor driven fan or air handlingdevice.
____ Belt tension and drive alignment.
____ Airflow at outlets with the thermostat adjusted to simulate full cooling, full heating, hood operation, etc. where appropriate.
____ Airflow ateach air handler at simulated full cooling and/or maximum fresh air.
____ Airflow at each fume hood based on sash positions.
____ Air flow at each range, dishwasher and process hood.
____ Room staticpressure with respect to adjacent spaces and outdoors.
____ Outside air rate into system.
____ Drafts or noise from air distribution devices.
2.0 PLUMBING AND PIPING SYSTEMS:
The CA willverify and report on the operation and accessibility of the following items.
2.1 EQUIPMENT
____ Sewage lift pump.
____ Sump pumps.
____ Chemical feed equipment.
____ Air compressor,de-ionized water equipment and other process equipment.
____ Pump motor current draw. Compare running current to nameplate full load amps rating. Overload heater size.
2.2 PIPING
____ Strainers,valves, fixtures, steam traps, air purge, and blow down systems, and instrumentation and flow measuring or control. Bypass and shut off valves for maintenance.
____ Cleaning, degreasing and flushing...