ETAPA 1 ( EN OBRA NEGRA)
INCLUYE MATERIAL E INSTALACION DE ACOMETIDA, CENTRO DE CARGA GENERAL, DUCTOS, CAJAS CHALUPA Y CAJAS DE PLAFON ENCIMBRA ANTES DEL COLADO DE TECHO.
TIEMPO DE ENTREGA 1 SEMANA
ETAPA 2
MATERIAL E INSTALACION DE CENTRO DE CARGA DE DISTRIBUCION, CABLEADO Y COLOCACION DE APAGADORES, CONTACTOS 2P+T, Y ROCETASCERAMICAS EN SALIDAS DE PLAFON ROSCA E60
TIEMPO DE ENTREGA 4 DIAS
MATERIALES
|DESCRIPCION |UNID. |CANT. |P.UNIT.|IMPORTE |
|ACOMETIDA 110V.30 AMP. MUFA, TUBO CONDUIT 1,1/4 “ BASE MEDICION, |PZA |1 |639 |639 |
|CABLE N.8 Y VARILLA A TIERRA| | | | |
|CENTRO DE CARGA DE 2 FUSIBLES 30 AMP.110V |PZA |1 |150|150 |
|POLIDUCTO ELECTRICO PVC FLEXIBLE ½ |ROOLO |1 |325 |325 |
|CAJAS 2X4 (CHALUPA) METALICA|PZA |31 |5.40 |176.4 |
|CAJAS HEXAG PLAFON 3X3 METAL |PZA |10|6.1 |61 |
|CINTA AISLANTE VINIL 3M |PZA |4 |11 |44 |
TOTAL DE MATERIAL 1ERETAPA $1395.4 NO INCLUYE IVA
MANO DE OBRA
|DESCIPCION |UNID. |CANT. |P. UNIT. |IMPORTE ||ACOMETIDA 110V 30 AMP. |PZA |1 |590 |590 |
|CENTRO DE CARGA 110V.2 FUSIBLES 30 AMP. |PZA...