| TC Company makes several printing works using two machines (X and Y). |
Data on the two machines for June 2010 are as follows: |
| X | Y |
Direct material | 10 | 15 |
Timerequired for each unit (TR) | 2 | 3 |
Expected volume during the month (EV) | 2,000 | 500 |
| | |
Expected labor cost per hour | 50 | |
Budgeted overhead costs | 660,000 | |
| | |Determine | | |
The total number of labor hours TC will work during June 2010. |
|
|
| Student Response | Value | Correct Answer | Feedback |
1. | 4,000 | | | |
2. | 5,500 |100% | | |
3. | 6,000 | | | |
4. | 6,500 | | | |
|
General Feedback: | 1) Determine the number of hours that should be worked next month
X Y Total
Time required for eachunit (TR) 2 3
Expected volume during the month (EV) 2,000 500
Expected hours needed = TR * EV 4,000 1,500 5,500 |
Score: | 1/1 |
|
|
2. | |
| TC Company makes several printingworks using two machines (X and Y). |
Data on the two machines for June 2010 are as follows: |
| X | Y |
Direct material | 10 | 15 |
Time required for each unit (TR) | 2 | 3 |
Expectedvolume during the month (EV) | 2,000 | 500 |
| | |
Expected labor cost per hour | 50 | |
Budgeted overhead costs | 660,000 | |
| | |
Determine | | |
The overhead rate per labor hour ||
|
| Student Response | Value | Correct Answer | Feedback |
1. | FOAR = $120.00 per hour worked | | | |
2. | FOAR = 120.00 per dollar | | | |
3. | FOAR = $60.00 perhour worked | | | |
4. | FOAR = $120.00 per overhead costs | 0% | | |
|
General Feedback: | 1) Determine the number of hours that should be worked next month
X Y Total
Timerequired for each unit (TR) 2 3
Expected volume during the month (EV) 2,000 500
Expected hours needed = TR * EV 4,000 1,500 5,500 |
Score: | 0/1 |
|
|
3. | |
| TC Company makes...