Costos y presupuestos
No | CONCEPTO | LUGAR | EJES | TRAMO | LARGO | ANCHO | ALTURA | PIEZAS | TOTAL | UN | OBSERVACIONES |
1 | Limpieza y despalme del terreno | TERRENO | 1 | A-I | 23.9 | 12.42 | | 1 | 285.00 | M2 | |
| | | | | | | | | | | |
| | | | | | | | | | | |
| | LOCALIZACIÓN | | | | | | | |
No | CONCEPTO | LUGAR | EJES | TRAMO | LARGO | ANCHO | ALTURA | PIEZAS | TOTAL | UN | OBSERVACIONES |
2 | TRAZO Y NIVELACION:Trazo y nivelación, estableciendo
ejes de referencia, incluye: materiales, mano de obra, equipo y herramienta. | TERRENO | 1 | A-I | 24.52 | | | 1 | | ml | |
| | | 2 | C-H | 13.22 | | | 1 | | | |
| | | 3 | F-G | 1.51 | | | 1 | | | |
| | | 4 | F-G | 1.69 | | | 1 | | | |
| | | 4 | G-H | 1.39 | | | 1 | | | |
| | | 5 | A-H | 18.41 | | | 1 | | | |
| | | 6 | G-H | 1.19 | | | 1 | | | |
| | | 7 | A-I | 24 | | | 1 | | | |
| | | B | 5--7 | 3.58 | | | 1 | | | |
| | | C | 2--5 | 3.58 | | | 1 | | | |
| | | D | 5--7 | 3.58 | | | 1 | | | |
| | | E | 2--7 | 7.16 | | | 1 | | | |
| | | F | 2--5 | 2.38 | | | 1 | | | |
| | | G | 2--7 | 5.96 | | | 1 | | | |
| | | H | 2--7 | 7.16 | | | 1 | | | |
| | | I | 1--7 | 11.23 | | | 1 | | | |
| | | | | 130.56 | | | | | | |
| |LOCALIZACIÓN | | | | | | | |
No | CONCEPTO | LUGAR | EJES | TRAMO | LARGO | ANCHO | ALTURA | PIEZAS | TOTAL | UN | OBSERVACIONES |
3 | EXCAVACION PARA CIMENTACION:Excavación de zanja, por medios manuales de 0 a -.60 m, en material tipo II, incluye:
mano de obra, equipo y herramienta. | TERRENO | 1 | A-I | 24.52 | 0.6 | 1 | | 14.7 | M3 | || | | 2 | C-H | 13.22 | 0.6 | 1 | | 7.932 | M3 | |
| | | 3 | F-G | 1.36 | 0.6 | 1 | | 0.816 | M3 | |
| | | 4 | F-G | 1.54 | 0.6 | 1 | | 0.924 | M3 | |
| | | 4 | G-H | 1.24 | 0.6 | 1 | | 0.744 | M3 | |
| | | 5 | A-H | 18.41 | 0.6 | 1 | | 11.046 | M3 | |
| | | 6 | G-H | 1.04 | 0.6 | 1 | | 0.624 | M3 | |
| | | 7 | A-I | 24 | 0.6 | 1 | | 14.4 | M3 | |
| | | B | 5--7 | 3.58 | 0.6 | 1 | | 2.148 | M3 | |
| | | C | 2--5 | 3.58 | 0.6 | 1 | | 2.148 | M3 | |
| | | D | 5--7 | 3.58 | 0.6 | 1 | | 2.148 | M3 | |
| | | E | 2--7 | 7.16 | 0.6 | 1 | | 4.296 | M3 | |
| | | F | 2--5 | 2.38 | 0.6 | 1 | | 1.428 | M3 | |
| | | G | 2--7 | 5.96 | 0.6 | 1 | | 3.576 | M3 | |
| | | H |2--7 | 7.16 | 0.6 | 1 | | 4.296 | M3 | |
| | | I | 1--7 | 11.23 | 0.6 | 1 | | 6.738 | M3 | |
| | | | | | | | TOTAL | 77.964 | M3 | |
| | LOCALIZACIÓN | | | | | | | |
No | CONCEPTO | LUGAR | EJES | TRAMO | LARGO | ANCHO | ALTURA | PIEZAS | TOTAL | UN | OBSERVACIONES |
4 | CIMENTACION:Piedra caliza de la región, resultado de laexcavación, adherido con un mortero de cemento – arena en una proporción de 6:1, debidamente entrañado, a plomo y nivel. | TERRENO | 1 | A-I | 20.7 | 0.3 | 1.3 | 1 | | ml | Sin incluir dados de cimentación |
| | | 2 | C-H | 11.28 | 0.3 | 1.3 | 1 | | | |
| | | 3 | F-G | 0.76 | 0.3 | 1.3 | 1 | | | |
| | | 4 | F-G | 0.94 | 0.3 | 1.3 |1 | | | |
| | | 4 | G-H | 0.64 | 0.3 | 1.3 | 1 | | | |
| | | 5 | A-H | 16.47 | 0.3 | 1.3 | 1 | | | |
| | | 6 | G-H | 0.64 | 0.3 | 1.3 | 1 | | | |
| | | 7 | A-I | 21.41 | 0.3 | 1.3 | 1 | | | |
| | | B | 5--7 | 3.82 | 0.3 | 1.3 | 1 | | | |
| | | C | 2--5 | 3.82 | 0.3 | 1.3 | 1 | | | |
| | | D | 5--7 | 3.82 | 0.3 | 1.3 | 1 |...