Ejemplo de plan de ejecución
Of
Esmeraldas Refinery Project (Phase I)
(Steel Structure)
Jun.21.2010
Structural Steel MGR
PART I. Steel Structure
Construction Schedule (Includingprefabrication, overbridge/local platform and shelter steel structure)
Work Volume.
Manpower Mobilization Plan.
Equipment Mobilization Plan.
Shop Drawing Handling Process
Material HandlingProcess.
Steel Structure Area Plan.
Construction Schedule (Including prefabrication, overbridge/local platform and shelter steel structure)
Steel Structure Work Volume
Manpower MobilizationPlan Work Volume
MAINTENANCE WORKSHOP AND EQUIPMENT
Installation
Training to personnel (60) from REE for each equipment to be acquired in number 3.1
Installation of 1 horizontal lathes 3meters between points, 6" spindle, swing 32", without neck.
Installation of 1 magnetic drill.
Installation of 1 vertical drill.
Installation of 1 universal milling machine.
Installation of 2 stoningmachine sets.
Installation of 2 hydraulic presses.
Installation of 1 portable purifier, 600 gl/h.
Installation of 2 plasma cutting.
Installation of 2 LINCOLN electric motor welding machines.Installation of 1 electric welding machines, 300 A transformers.
Installation of 6 electric motor tool (choke grinder).
Installation of 1 hydraulic roller for metal plate, 1/8" through 5/8" thickness.Installation of 1 metal plate hydraulic bending machine.
Installation of 1 torque equipment SQD from 160 through 180 lb-ft, with pump PTA 3408 hydraulic or pneumatic.
Installation of 1 pneumaticcompressor, 125 ATLAS COPCO, of 10 bar.
Installation of 2 14"-wheel electric cutting machine.
Project Scope, Objectives and Deliverables.
The objective is Esmeraldas Refinery Rehabilitation.GENERAL SCOPE OF WORK
HEAVY EQUIPMENT ERECTION |
|
1.- | Documents and Drawings | | | | | | | | |
| 1.1 | Construction Work plans, Procedures and Methodology | | | |...