01.01 CASETA ALMACEN Y GUARDIANIA glb 1.00 1,000.00 1,000.00
01.02 CARTEL DE IDENTIFICACION DE LA OBRADE 3.60 X 2.40 m u 1.00 610.09 610.09
02 TRABAJOS PRELIMINARES 312.93
02.01 TRAZO Y REPLANTEO DE OBRA OBRA m 137.25 2.28 312.93
03MOVIMIENTO DE TIERRAS 64,696.54
03.01 EXCAVACION EN TERRENO ROCOSO m3 1,273.54 34.44 43,860.72
03.02 RELLENO COMPACTADO CON MATERIAL PROPIOm3 544.62 17.78 9,683.34
03.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 728.92 15.30 11,152.48
04 OBRAS DE CONCRETO 127,067.3404.01 SOLADOS EN MUROS E=10cm m2 274.50 17.24 4,732.38
04.02 ENCOFRADO Y DESENCOFRADO NORMAL PARA ZAPATAS m2 171.90 38.37 6,595.8004.03 CONCRETO f'c=175 kg/cm2 + 70% DE PIEDRA GRANDE ASENTADA EN ZAPATAS m3 137.25 191.66 26,305.34
DE MURO DE MANPOSTERIA PARA ZAPATAS04.04 ENCOFRADO Y DESENCOFRADO EN MUROS m2 724.33 44.99 32,587.61
04.05 CONCRETO f'c=175 kg/cm2 + 70% DE PIEDRA GRANDE ASENTADA EN MUROS DE m3274.50 207.09 56,846.21
MANPOSTERIA
05 JUNTAS 1,828.36
05.01 JUNTAS EN MURO CON TEKNOPORT E=1" m2 77.44 23.61 1,828.36
COSTO DIRECTO195,515.26
GASTOS GENERALES 10% 19,551.53
UTILIDAD 8% 15,641.22
---------
SUBTOTAL 230,708.01
IMPUESTO (IGV)18% 41,527.44
=========
TOTAL PRESUPUESTO 272,235.45
SON : DOSCIENTOS SETENTIDOS MIL DOSCIENTOS TRENTICINCO Y 45/100 NUEVOS SOLES