Ingenieria
|Trade |Activities |STEPS |Weight % |
|Civil Work |Site conditioning |N/A | |
| |Piling |Fabrication|30 |
| |(N/A) |Pile Driving |60 |
| | |Head removal |10 |
| | || |
| | | | |
| |Equipment and Structures |Excavation and lean concrete. |10 |
| |Foundations |Reinforcements preparation.|25 |
| | |Formworks. |15 |
| | |Concrete casting. |30 |
| | |Stripping.|10 |
| | |Backfilling. |5 |
| | |Final check & QA/QC certif. |5 |
| |Concrete Structures |Reinforcement.|30 |
| | |Formworks. |10 |
| | |Concrete casting. |40 |
| | |Stripping |10|
| | |Final check & QA/QC certif. |10 |
| |Buildings |Excavation & Backfilling |10 |
| |Concrete |Foundation & Lean |10|
| | |Pillars & Beams |20 |
| | |Slabs ( ground level ) |15 |
| | |External Walls ( Brick ) |4|
| | |Roof Water Proofing |10 |
| | |Floors |2 |
| | |Internal Walls |2 || | |Ceilings |3 |
| |Architecture |Walls Finishing |2 |
| | |Plumbing & Draining |5 |
|...