Matematicas financira
FLUJO DE CAJA 0 | -18000 | -23000 |
FLUJO DE CAJA 1 | 4000 | 4000 |
FLUJO DE CAJA 2 | 4000 | 6000 |
FLUJO DE CAJA 3| 4000 | 7000 |
FLUJO DE CAJA 4 | 8000 | 8000 |
FLUJO DE CAJA 5 | 8000 | 9000 |
FLUJO DE CAJA 6 | 8000 | 10000 |
PROYECTO A FLUJO DE CAJA O | -18000 | Tasa de oportunidad | 15,00% |FLUJO DE CAJA 1 | 4000 | | |
FLUJO DE CAJA 2 | 4000 | | |
FLUJO DE CAJA 3 | 4000 | | |
FLUJO DE CAJA 4 | 8000 | | |
FLUJO DE CAJA 5 | 8000 | | |
FLUJO DE CAJA 6 |8000 | | |
TIR | 20,34% | TIR(B1:B7) | |
VPN | 3142,96 | VNA(D1;B2:B7)+B1 | |
| | | |
PROYECTO B | | | |
| | | |
FLUJO DE CAJA O | -23000 | Tasa de oportunidad| 15,00% |
FLUJO DE CAJA 1 | 4000 | | |
FLUJO DE CAJA 2 | 6000 | | |
FLUJO DE CAJA 3 | 7000 | | |
FLUJO DE CAJA 4 | 8000 | | |
FLUJO DE CAJA 5 | 9000 | | |
FLUJODE CAJA 6 | 10000 | | |
TIR | 19,05% | TIR(B1:B7) | |
VPN | 2989,63 | VNA(D1;B2:B7)+B1 | |
| | | |
TASA VERDADERA PROYECTO AF1 = 4000(1+0.15)⁵ = $1988,71F2 =4000(1+0.15)4= $2287,01F3 = 4000(1+0.15)³ = $2630,03F4 = 8000(1+0.15)² = $6049,15F5 = 8000(1+0.15)¹ = $6956,52F6 = 8000(1+0.15)⁰ = $8000F = F1+ F2+ F3 + F4 + F5 + F6 = 27911,4627911,46
-18000
0...