Numeros generadores
TRABAJOS PRELIMINARES
CONCEPTO | EJE | TRAMO | UNIDAD | LONGITUD | ANCHO | SUPERFICIE DE VOLUMEN |
LIMPIEZA DEL TERRENO | A | 1-3 | M² | 4.577 | 7.000 | 32.039 |
| | | | | | | | TOTAL | 32.039 |
CONCEPTO | EJE | TRAMO | UNIDAD | LONGITUD | ANCHO | SUPERFICIE DE VOLUMEN |
TRAZO Y NIVELACIÓN | A | 1-3 | M² | 4.577 | 7.000 | 32.039 |
| | | | | | | |TOTAL | 32.039 |
CONCEPTO | EJE | TRAMO | UNIDAD | LONGITUD | ANCHO | ALTURA | SUPERFICIE DE VOLUMEN |
EXCAVACIÓN DE SEPAS | A | 1-3 | M³ | 5.450 | 1.000 | 0.950 | 5.178 |
| C | 1-3 | M³ | 5.450 | 1.000 | 0.950 | 5.178 |
| B | 2-3 | M³ | 0.450 | 0.997 | 0.950 | 0.426 |
| 1 | A-C | M³ | 3.450 | 1.000 | 0.950 | 3.278 |
| 3 | A-C | M³ | 3.450 | 1.000 | 0.950 | 3.278 |
| 2 | B-C| M³ | 0.450 | 1.000 | 0.950 | 0.428 |
| | | | | | | | TOTAL | 17.764 |
CIMENTACIÓN
CONCEPTO | EJE | TRAMO | UNIDAD | LONGITUD | ANCHO | ALTURA | SUPERFICIE DE VOLUMEN |
CONCRETO PARA PLANTILLA | A | 1-3 | M³ | 5.450 | 1.000 | 0.050 | 0.273 |
| C | 1-3 | M³ | 5.450 | 1.000 | 0.050 | 0.273 |
| B | 2-3 | M³ | 0.450 | 0.997 | 0.050 | 0.022 |
| 1 | A-C | M³ | 3.450 | 1.000 |0.050 | 0.173 |
| 3 | A-C | M³ | 3.450 | 1.000 | 0.050 | 0.173 |
| 2 | B-C | M³ | 0.450 | 1.000 | 0.050 | 0.023 |
| | | | | | | | TOTAL | 0.935 |
CONCEPTO | EJE | TRAMO | UNIDAD | LONGITUD | AREA TRANSVERSAL | SUPERFICIE DE VOLUMEN |
VOLUMEN DE ROCA PARA Z-1 | A | 1-3 | M³ | 5.450 | 0.713 | 3.886 |
VOLUMEN DE ROCA PARA Z-2 | C | 1-3 | M³ | 5.450 | 0.713 | 3.886 |
| B |2-3 | M³ | 0.450 | 0.713 | 0.321 |
| 1 | A-C | M³ | 3.450 | 0.713 | 2.460 |
| 3 | A-C | M³ | 3.450 | 0.713 | 2.460 |
| 2 | B-C | M³ | 0.450 | 0.713 | 0.321 |
| | | | | COEFICIENT DE ABUN | TOTAL | 13.333 |
| | | | | 1.5 | VOLUMEN TOTAL | 20.000 |
CONCEPTO | EJE | TRAMO | UNIDAD | LONGITUD | ANCHO | ALTURA | SUPERFICIE DE VOLUMEN |
CONCRETO PARA CADENA DE DESPLANTE (D-C)| A | 1-3 | M³ | 4.380 | 0.300 | 0.200 | 0.263 |
| C | 1-3 | M³ | 4.380 | 0.300 | 0.200 | 0.263 |
| B | 2-3 | M³ | 0.600 | 0.300 | 0.200 | 0.036 |
| 1 | A-C | M³ | 4.150 | 0.300 | 0.200 | 0.249 |
| 3 | A-C | M³ | 4.150 | 0.300 | 0.200 | 0.249 |
| 2 | B-C | M³ | 0.600 | 0.300 | 0.200 | 0.036 |
| | | | | | | | TOTAL | 1.096 |
CONCEPTO | EJE | TRAMO | UNIDAD | LONGITUD |NUMERO DE VARILLAS | SUPERFICIE DE VOLUMEN |
ACERO DE REFUERZO CON 4 VAR Ø 3/8'' PARA CADENA DE DESPLANTE (D-C) | A | 1-3 | ML | 4.560 | 4.000 | 18.240 |
| C | 1-3 | ML | 4.560 | 4.000 | 18.240 |
| B | 2-3 | ML | 1.080 | 4.000 | 4.320 |
| 1 | A-C | ML | 4.560 | 4.000 | 18.240 |
| 3 | A-C | ML | 4.560 | 4.000 | 18.240 |
| 2 | B-C | ML | 1.080 | 4.000 | 4.320 |
| | | | | || | TOTAL | 81.600 |
CONCEPTO | EJE | TRAMO | UNIDAD | LONGITUD | N° ESTRIBOS | LONG ESTR | SUPERFICIE DE VOLUMEN |
ACERO DE REFUERZO CON EST Ø 1/4'' PARA CADENA DE DESPLANTE (D-C) | A | 1-3 | ML | 4.560 | 23.000 | 0.920 | 21.160 |
| C | 1-3 | ML | 4.560 | 23.000 | 0.920 | 21.160 |
| B | 2-3 | ML | 1.080 | 6.000 | 0.920 | 5.520 |
| 1 | A-C | ML | 4.560 | 23.000 | 0.920 | 21.160 || 3 | A-C | ML | 4.560 | 23.000 | 0.920 | 21.160 |
| 2 | B-C | ML | 1.080 | 6.000 | 0.920 | 5.520 |
| | | | | | | | TOTAL | 95.680 |
ALBAÑILERÍA
CONCEPTO | EJE | TRAMO | UNIDAD | LONGITUD |
CADENA DE CERRAMIENTO (D-M) 0.30X0.15 (m) PRIMER NIVEL | A | 1-3 | ML | 4.600 |
| C | 1-3 | ML | 4.600 |
| B | 2-3 | ML | 0.600 |
| 1 | A-C | ML | 4.300 |
| 3 | A-C | ML |4.300 |
| 2 | B-C | ML | 0.600 |
| | | | | TOTAL | 19.000 |
CONCEPTO | EJE | TRAMO | UNIDAD | LONGITUD | NUMERO DE VARILLAS | SUPERFICIE DE VOLUMEN |
ACERO DE REFUERZO CON 4 VAR Ø 3/8'' PARA CADENA DE CERRAMIENTO (D-M) | A | 1-3 | ML | 4.660 | 4.000 | 18.640 |
| C | 1-3 | ML | 4.660 | 4.000 | 18.640 |
| B | 2-3 | ML | 0.660 | 4.000 | 2.640 |
| 1 | A-C | ML | 4.660 | 4.000 |...