PRECIO UNITARIO

LIMPIA Y TRAZO M2

CLAVE CONCEPTO UNIDAD CANTIDAD PRECIO IMPORTE

MATERIAL:
CALIDHRA KG 0.04 $1.00 $0.04
HILO KG 0.0017 $100.00 $0.17
ESTACAS PZA 8.76 $4.57 $40.04
SUBTOTAL $40.25

MANO DE OBRA:

CUAD.2 JOR 0.005$1,876.63 $9.38


SUBTOTAL $9.38
EQUIPOS Y HERRAMIENTA:

HERRAMIENTA MENOR % 0.03 $9.38 $0.28

SUBTOTAL $0.28




TOTAL COSTO DIRECTO $49.92
25% COSTOS INDIRECTOS $12.48
PRECIO UNITARIO $62.40 M2PRECIO UNITARIO
CONTTRATRABE ML

B CONC M3 0.125 $784.13 $98.02
B, A 1/2 TON 0.006 $13,374.00 $80.24
B A 3/8 TON 0.005 $13,445.00 $67.23
CIMBRA M2 1 $47.74 $47.74


SUBTOTAL $293.23
MANO DE OBRA M3 ML COSTO ML
CUA 2 JOR. 0.0208 $1,876.64 $39.031876.64 6 312.7733333 0.125 39.09666667
CUA 4 JOR. 0.0176 $1,336.41 $23.52 1 6 0.166666667 0.125 0.020833333
CUA 4 JOR. 0.0147 $1,336.41 $19.65 0.125 6 0
CUA 3 JOR. 0.1 $952.55 $95.26
SUBTOTAL $177.46 CANT/ML REND/ JOR JORNADA
,125 6 M3 0.0208
0.006 0.34 TON 0.0176
0.005 0.34 TON 0.0147
1 10 M2 0.1CARRETILLA PZA VIDA UTIL
1000 M3 V U 0.000125 $450.00 $0.06 0.125 1000 0.000125
REVOL HORA 0.05 $396.65 $19.83 0.125 2.5 0.05 480
VIBRASOR HORA 0.05 $63.91 $3.20 0.125 2.5 0.05 480
CORTADORA DE VARILL PZA 0.000044 $3,500.00 $0.15 0.005 0.006 0.011 250 0.000044
V. 3/8 V. 1/2
$23.24


TOTAL C.DINDIRECTOS




PRECIO UNITARIO
COLUMNA ML
M3 DE CONC
B CONC M3 0.18 $784.13 $141.14 0.4 0.45 1 0.18
B, A 3/4 TON 0.01808 $14,913.80 $269.64 20 2.26 1 45.2 2.5
B, A 1/2 TON 0.00792 $13,374.00 $105.92 20 0.99 1 19.8 2.5
B A 3/8 TON 0.0174 $13,445.00 $233.94 1.7 0.57 3028.666250 2.5
CIMBRA M2 1.7 $62.90 $106.93


SUBTOTAL $857.58
MANO DE OBRA CANTID RENDIM JORNADA
CUA 2 JOR. 0.0529 $1,876.64 $99.35 0.18 3.4 0.0529
CUA 4 JOR. 0.0563 $1,336.41 $75.17 0.018 0.32 0.0563
CUA 4 JOR. 0.0247 $1,336.41 $32.99 0.0079 0.32 0.0247
CUA 4 JOR. 0.0359 $1,337.41 $48.06 0.0115 0.32 0.0359
CUA3 JOR. 0.2267 $952.55 $215.91 1.7 7.5 0.2267
SUBTOTAL $471.49

H. MENOR 0.03
CARRETILLA PZA
1000 M3 V U 0.000125 $450.00 $0.06
REVOL HORA 0.05 $396.65 $19.83
VIBRASOR HORA 0.05 $63.91 $3.20
CORTADORA DE VARILL PZA 0.000044 $3,500.00 $0.15

$23.24TOTAL C.D
INDIRECTOS




TRABE ML

B CONC M3 0.125 $784.13 $98.02 0.5 0.25 1 0.125
B, A 3/4 TON 0.0068 $14,913.80 $101.41 3 2.26 1 0.007
B, A 1/2 TON 0.0059 $13,374.00 $78.91 6 0.99 1 0.006
B A 3/8 TON 0.0071 $13,445.00 $95.46 8.333333333 0.57 1.5 0.007
CIMBRA M2 1.25$82.75 $103.44 1.25 1 1.250


SUBTOTAL $477.23
MANO DE OBRA CANTID RENDIM JORNADA
CUA 2 JOR. 0.0368 $1,876.64 $68.99 0.125 3.4 0.0368
CUA 4 JOR. 0.0213 $1,336.41 $28.40 0.0068 0.32 0.0213
CUA 4 JOR. 0.0184 $1,336.41 $24.64 0.0059 0.32 0.0184
CUA 4 JOR. 0.0222 $1,337.41 $29.67 0.0071 0.32 0.0222
CUA 3 JOR....
Leer documento completo

Regístrate para leer el documento completo.

Estos documentos también te pueden resultar útiles

  • padron de contratistas
  • Formatos de padrón de contratistas
  • Padrón De Contratistas
  • Padron al contratista
  • REQUISISTOS PADRON DE CONTRATISTAS Y RENOVACIONES 2015 2018
  • REQUISITOS PADRON CONTRATISTA
  • La serva padrona
  • Padron de importadores

Conviértase en miembro formal de Buenas Tareas

INSCRÍBETE - ES GRATIS