STEAM TURBINE ERECTION PROCEDURE
rev.
Pagina
of
1
2
0408 TXMA*S553
Di
page
50
Classe di Riservatezza
confidential class
Volume N.
2
Prodotto/Struttura
volume no.
product/structure
DA901
Tipo doc.
Codice
EmittenteTeamcenter
doc. type
Ente Emittente
issued by
teamcenterissuer code
FSP
Commessa
Progetto
job no.
POSCO E&C
Descrizione
rev.
kind of revision
First issue
Revised paragraph: 1.3; 2.4; 3.2; 4; 6; 7; 8; 10.1; 10.2
Added dwg. missing
2
Montelatici
Beiso
Cagliani
Vacca
10/03/10
1
Montelatici
Beiso
Cagliani
Vacca
10/06/09
25/03/09
0
Rev
rev.
Montelatici
Scopo
scope
BeisoCagliani
Vacca
TVP/VAVV
TVP/VAVV
TVP/CTEC
TVP/VAVV
Preparato
Controllato
Verificato
Approvato
prepared
Verificato
checked
verified
posco
verified
Approved
Data
Date
HYUNDAI
ENGINEERING CO.. LTD.
ANGAMOS
TITLE THERMOELECTRIC
STEAM TURBINE ERECTION PROCEDURE
POWER PLANT
PREPARED
Posco
ELECT.SIGN D:Montelatici C:Beiso A1:CaglianiA2:Vacca A3:- (11/03/2010)
rev.
ENG
client
Rev.
0
1
2
Rev.
derived from
Cliente
ANGAMOS
0408T1/T2
Derivato da
language
TVP/VAVV
VPFO
project
Edizione in lingua
SIGNA
TURE
DATE
CHECKED
REVIEWED
APPROVED
Posco
DWG
no.
0-WD210-ER630-00553
Ansaldo Energia s.p.a. si riserva tutti i diritti su questo documento che non può essereriprodotto neppure parzialmente senza la sua autorizzazione scritta
Ansaldo Energia s.p.a. reserves all rights on this document that can not be reproduced in any part without its written consent
Progetto / Titolo
Project / title
0408 – ANGAMOS
STEAM TURBINE ERECTION PROCEDURE
Identificativo
document no.
0408 TXMA*S553
Rev.
rev.
2
Pagina
page
2
50
Classe diRiservatezza
confidential class
List of contents
0.
INTRODUCTION
1.
1.1
1.2
1.3
FOUNDATION INSERTS AND ANCHORS
Installation and checks of the foundation inserts before and after concrete casting
Installation of the foundation sole plates and anchors
Oil tanks and other steam turbine auxiliary embedded parts
2.
2.1
2.2
2.3
2.4
2.5
LP SECTION
Positioning the outer casing ofthe LP section
Welding of the LP outer casing to the condenser neck
Assembly of LP inner casing and gland seal casings
Assembly of the LP rotor
Alignment of the LP gland seal casings and closure of the LP section
3.
3.1
3.2
3.3
3.4
STEAM TURBINE SUPPORTS
Installation of the pedestals
Final assembly of the pedestals and assembly of the auxiliary bearings
Bearing assembly andpedestal key final assembly
Assembly of the upper parts of the pedestals
4.
IP SECTION
5.
HP SECTION
6.
CROSS OVER
7.
7.1
7.2
7.3
ASSEMBLY OF VALVE AND SERVOMOTORS
Installation of main steam valves
Hydrostatic test, acid cleaning and steam blowing
Check of the valve cover tightness and coupling of the actuators to the valves
8.
MAIN STEAM AND EXTRACTION PIPING
9.9.1
9.2
ASSEMBLY OF STEAM TURBINE AUXILIARIES AND RELATED PIPING
Steam turbine auxiliaries
Steam turbine related piping
10.
10.1
10.2
ROTOR ALIGNEMENT
Rotor alignment and finish machining of the coupling bolt holes
Final check of the alignment and final closure of the couplings
11.
INSTALLATION OF THE ELECTRIC COMPONENETS AND CABLING
12.
INSULATION
13.CERTIFICATE LIST
APPENDIX A
Di
of
2
Progetto / Titolo
Project / title
0408 – ANGAMOS
STEAM TURBINE ERECTION PROCEDURE
Identificativo
document no.
0408 TXMA*S553
Rev.
rev.
2
Pagina
page
3
50
Classe di Riservatezza
confidential class
0.
Di
of
2
INTRODUCTION
This procedure refers to the field assembly of the steam turbine type RT rated 270 MW...