Tareas
| | | | | |
| | | | | |
1 | | PRELIMINARES | | | 4.48 |
| 01 | Limpieza Inicial | m2 |8875.00 | 4.48 |
2 | | TOPOGRAFIA | | | 1.25 |
| 01 | Trazo y Nivelación | Ml | 1250.00 | 1.25 |
3 | | MOVIMIENTOS DE TIERRA | | | 18.09 |
| 01 | Corte de Material Rocoso | m3 |975.00 | 3.30 |
| 02 | Corte de Material Arcilloso | m3 | 2715.48 | 5.98 |
| 03 | Relleno Compensado | m3 | 375.24 | 1.62 |
| 04 | Desalojo de Material Rocoso | m3 | 399.52 | 0.58 |
| 05 |Desalojo de Material Arcilloso | m3 | 3122.80 | 4.51 |
| 06 | Compactación | m2 | 8875.00 | 2.103 |
3 | | Estabilización de Taludes | | | 7.6 |
| 01 | Corte de Material Rocoso | m3 | 266.67| 0.73 |
| 02 | Corte de Material Arcilloso | m3 | 1640.41 | 3.67 |
| 03 | Desalojo de Material Rocoso | m3 | 333.34 | 0.48 |
| 04 | Desalojo de Material Arcilloso | m3 | 1886.47 | 2.72 |4 | | Bombeo en Camino | | | 3.63 |
| 01 | Corte de Material Rocoso | m3 | 101.25 | 0.34 |
| 02 | Relleno Compensado | m3 | 451.44 | 1.96 |
| 03 | Compactación | m2 | 5625.00 | 1.33 |5 | | Cunetas Revestidas(Concreto Ciclópeo) | | | 31.462 |
| 01 | Corte de Material Rocoso | m3 | 180.00 | 1.27 |
| 02 | Corte de Material Arcilloso | m3 | 425.52 | 3.022 |
| 03 |Desalojo de Material Rocoso | m3 | 225.00 | 0.32 |
| 04 | Desalojo de Material Arcilloso | m3 | 489.35 | 0.71 |
| 05 | Compactación | m2 | 1970.81 | 0.08 |
| 06 | Concreto Ciclópeo | m3 | 371.41| 26.06 |
6 | | Vado | | | 0.6779 |
| 01 | Corte de Material Rocoso | m3 | 3.18 | 0.02 |
| 02 | Corte de Material Arcilloso | m3 | 12.72 | 0.09 |
| 03 | Desalojo de Material Rocoso |m3 | 3.97 | 0.0056 |
| 04 | Desalojo de Material Arcilloso | m3 | 14.63 | 0.021 |
| 05 | Compactación | m2 | 32.26 | 0.0013 |
| 06 | Concreto Ciclópeo | m3 | 7.68 | 0.54 |
7 | |...