Wiro
CANTIDAD A LA MANO: 50 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
PRONOSTICO | 19 | 16 | 15 | 20 | 20 | 21 | 22 | 19 | 20 | 23 |
PEDIDO DE LOS CLIENTES | 14| 18 | 16 | 19 | 26 | 19 | 26 | 18 | 22 | 17 |
INVENTARIO PROYECTADO A LA MANO | 31 | 13 | -3 62 | 42 | 16 | -5 60 | 34 | 15 | -7 58 | 35 |
CANTIDAD A LA MANO MPS | 0 | 0 | 65 | 0| 0 | 65 | 0 | 0 | 65 | 0 |
INICIO DEL MPS | 65 | 0 | 0 | 65 | 0 | 0 | 65 | 0 | 0 | 0 |
ATP | 18 | 0 | 4 | 0 | 0 | 2 | 0 | 0 | 26 | 0 |
POLITICA DE CALIDAD: 65
TIEMPO DE ENTREGA:1 DIA
INV. A LA MANO CANT. DEL MPSREY PROY.
INV. PROYECTADO A LA MANO = AL FINAL DE LA + AL INICIO DE - ESTA SEMANA
ÚLTIMA SEMANAESTA SEMANA
50+0-19= 3131+0-18= 1313+0-16= -313+65-16= 6262+0-20= 4242+0-26= -516+65-21= 6060+0-26= 3434+0-19= 1515+0-22= -715+65-23= 35 |
DISPONIBLECANTIDAD A CANTIDAD EN PEDIDOS REGISTRADOS
PARA PROMESA = LA MANO EN + EL MPS EN - HASTA LA SEMANA
EN LA SEMANA 1 LA SEMANA 1 LA SEMANA 1QUE LLEGARA EL SIG MPS
ATP DIA 1= 50+0-32=18
PEDIDOS REGISTRADOS
ATP = CANTIDAD EN EL MPS - HASTA LA SEMANA CUANDOLLEGARA EL SIGUIENTE MPS
ATP DIA 3= 65 – (16+19+26)= 4
ATP DIA 6= 65 – (19+26+18)= 2
ATP DIA 9= 65 – (22+17) = 26
INSTITUTOTECNOLOGICO SUPERIOR DE SAN PEDRO
MC: EDGAR OSVALDO ROSAS MEZA
RUBEN HUMBERTO GARCIA VILLANUEVA
MARIA AURORA TORRES EL TORO
ADMINISTRACION DE OPERACIONES II
5 “A”
23/SEP/2011