Manual Leica Tc400
For Use With The Leica TC407 Total Station
CEE121 Introduction to Civil and Environmental
Engineering Measurements
Created by
Kane C. Bennett
Reviewed by
Stacy A. Metzger
Don J. DeGroot
Civil and Environmental Engineering
University of Massachusetts Amherst
Amherst, Massachusetts 01003
August 2006
TABLE OF CONTENTS
Page
LIST OF SYMBOLS........................................................................................................ ii
1.0 INTRODUCTION....................................................................................................... 1
2.0 EQUIPMENT AND ORGANIZATION ................................................................... 1
3.0 GETTING STARTED................................................................................................ 1
3.1 PROCEDURE FOR SETTING UP AND LEVELING ....................................... 2
4.0 INTERFACING WITH THE TC407 ........................................................................ 3
4.1 THE KEYS OF THE TC407 .................................................................................. 4
4.2 LIST OF FIXEDKEYS.......................................................................................... 6
4.3 LIST OF GENERAL SOFTKEYS ........................................................................ 7
4.4 INPUT AND EDIT MODES .................................................................................. 8
5.0 AS-BUILT SURVEY .................................................................................................. 86.0 TOPOGRAPHIC SURVEY FROM A KNOWN POINT ....................................... 9
7.0 SURVEY TO OBTAIN AREA ................................................................................ 11
CONCLUSION ............................................................................................................... 12
REFERENCES................................................................................................................ 13
i
LIST OF SYMBOLS
T.S.
=
Total Station
PtID
=
Point ID
IR
=
Infrared laser
RL
=
Red Laser
Hz
=
Horizontal angle
∆Lin =
Distance down a baseline
∆Off =
Distance off of a baseline
East
Easting
=
North =
Northing
Height =
Elevation
E0
=
Station Easting
N0=
Station Northing
H0
=
Station Elevation
hi
=
Height of instrument as measured from the ground surface to the “tilting”
or “Trunion” axis.
hr
=
EDM =
Reflector height
Electronic Distance Measurement
ii
1.0 INTRODUCTION
This document is meant to serve as a guide and reference for the use of the Leica
TC407 Total Station in the CEE 121 Civil andEnvironmental Engineering Measurements
class at the University of Massachusetts Amherst. The general use and operation of the
TC407 is discussed as well as the specific operations: 1) a topographic survey, 2) a
survey to calculate area, and 3) an “as-built” survey.
2.0 EQUIPMENT AND ORGANIZATION
It is important to have a plan for every survey. The goals, methods, and general
approach should bediscussed before the survey begins. A list of equipment should be
compiled, the batteries should be charged, and each member of the survey crew should
have an understanding of what is happening and what their specific responsibilities will
be during the survey. The method of note taking should also be discussed beforehand,
and the note taker and surveyor (if different) should maintain frequentcommunication
and discussion throughout the survey. It may be preferable, for educational reasons, to
alternate responsibilities over the course of the survey so that each member of the crew
learns the various crew duties.
3.0 GETTING STARTED
Once you are at the location of the survey with all your equipment, it is a good
idea to “walk over” the survey site and consider suitable instrument...