METHOD STATEMENT FOR INSTRUMENT INSTALLATION 031014 Spanish
FOR CONSTRUCTION
1
SEP. 27,14
0
SEP. 13,14
REV.
DATE
EMPLOYER :
FOR CONSTRUCTION
FOR CONSTRUCTION
DESCRIPTION
FC
FC
DSGN
JM
JM
CHKD
JM
JM
APPD
Termotasajero S.A ESP
CONTRACTOR
SUB-CONTRACTOR
PROJECT
Termotasajero 2
DESIGNED BY
FC
CHECKED BY
JM
161.6MW CFPP
TITLE :
DATE
SEP,13,14
DATE
METHOD STATEMENT PARA
SEP,13,14 INSTALACION DEINSTRUMENTOS
APPROVED BY
DATE
DOCUMENT NUMBER
PROJECT
REV
JM
SEP,13,14
TT2-HEC-J810-0011
6548
1
TERMOTASAJERO II Net 160MW Coal Fired Power Plant
TABLA DE CONTENIDO
1.
ALCANCE………………………………………………………………………. ................. 3
2.
DOCUMENTOS DE REFERENCIA…………………………………………………………
3.
PERSONAS A CARGO…………………………………………………………. ............... 3
4.
EQUIPOS Y HERRAMIENTAS…………………………………………………………...3
5.
INSTALACION LOCAL DE INSTRUMENTOS……………………………………......... 4
6.
PROCEDIMIENTO DE VERIFICACION…………………………………………………
4
7.
PRUEBA E INSPECCION……………………………………………………………...
5
8.
ASPECTOS DE SEGURIDAD Y RIESGOS………………………………………………… 5
METHOD STATEMENT PARA INSTALACION DE
INSTRUMENTOS
3
TERMOTASAJERO II Net 160MW Coal Fired Power Plant
1. ALCANCE
Esta Descripción del Método cubre actividadespara la instalación de Instrumentación de
acuerdo con los planos oficiales, especificaciones, normas y estándares.
2. DOCUMENTOS DE REFERENCIA
AHS P&ID
Boiler ILD 140911
Boiler P&ID_Rev4_131223
BOP ILD_20140725
CFS P&ID
CHS P&ID
CTW ILD 20140627
F5451A13-IT-E-001 Instrument Layout(cooling tower)
FGD P&ID
Method statementof instrument installation
TT2-700-J171-00000 BOP ILD
TT2-700-J175-00001 Instrument Installation Drawing
TT2-ACS-M103-00001 P&ID
TT2-ACS-M103-00002 P&ID
TT2-ACS-M103-00003 P&ID
TT2-AHS-J171-00100 FA Instrument Arrangement Plan
TT2-AHS-J171-00200 BA Instrument Arrangement Plan
TT2-AHS-J175-00100 FA Hook up
TT2-BFP-M103-00001 P&ID
TT2-CEP-J103-00001 P&ID
TT2-CEP-J103-00002 P&ID
TT2-CFS-M101-00001GA
TT2-CFS-R103-00001 P&ID
TT2-CFS-R103-00002 P&ID
TT2-CHS-J171-00001 Instrument Location
TT2-CON-E170-00004 VP P&ID
TT2-CWP-J103-00001 P&ID
TT2-CWP-J103-00002 P&ID
TT2-EDG-M103-00001 P&ID
TT2-FGD-J171-00001 Instrument Location
TT2-FGD-J175-00001 Hook up
TT2-GSP-M440-00001 Equipment List
TT2-STG-J171-00012 Location
TT2-STG-J171-00013 Location
TT2-STG-J171-00032 Location
TT2-STG-J171-00033 LocationTT2-STG-M103-00010 P&ID
TT2-SUP-M130-00001 GA
METHOD STATEMENT PARA INSTALACION DE
INSTRUMENTOS
TERMOTASAJERO II Net 160MW Coal Fired Power Plant
TT2-WWS-J175-00001 Hook up
TT2-WWS-P142-00001 Pipe Arrangement Instrument location
TT2-WWS-R103-00001 P&ID
TT2_P&ID_20140509
WWS ILD 140701
All drawings for Instrument Suppliers
3. PERSONAS A CARGO
Superintendente Eléctrico deConstrucción
: José Pabón
Control de Materiales
: Josue Patiño
Supervisor C&I
: Félix Cáceres
Supervisor QA/QC
: Manuel Mesías
Técnicos y auxiliares C&I
4. EQUIPOS Y HERRAMIENTAS
Caja de Herramientas.
Taladro.
Martillo.
Nivel.
Metro.
Arnés con eslingas.
Cortatubos para Tubing.
Mechero para Tubing.
Doblatubo para Tubing.
5. INSTALACION LOCAL DE INSTRUMENTOS
Trabajo de instalación local de instrumentos.
a) Transmisores de Flujo, Presión, Nivel y Temperatura.
b) Interruptores de Flujo, Presión, Nivel y Temperatura.
c) Indicadores de Flujo, presión, nivel y temperatura.
d) Indicadores de PH.
e) Indicadores de Turbiedad.
Instalar los instrumentos según los detalles del fabricante y los “como indica el fabricante
incluyendo dirección y ubicación.Instalar el soporte o soportes a estructure donde sea necesario, como se observa en los
planos.
Proteger los instrumentos contra materiales externos de posible daño o ruptura durante el
periodo de construcción.
Instalar parasoles para evitar la exposición al sol y altas temperaturas, los instrumentos que
METHOD STATEMENT PARA INSTALACION DE
INSTRUMENTOS
TERMOTASAJERO II Net 160MW Coal Fired...
Regístrate para leer el documento completo.