Conservacion de carreteras
|
|
SUBSECRETARIA DE INFRAESTRUCTURA |
DIRECCION GENERAL DE CONSERVACION DE CARRETERAS |
Programa Nacional de Conservación deCarreteras |
SEPTIEMBRE 2010 |
No. | NOMBRE DE LA OBRA | UBICACION | META | TOTAL
ASIGNACION | AVANCE FISICO | AVANCE
FINANCIERO % |
| | | | | UNIDAD | % | |
| BAJA CALIFORNIA SUR | | | 313,711,500.00 | | 94.0 | 86.4 |
| | | | | | | |
| Conservación Periódica | | 132.00 | 206,125,000.00 | | 100.0 | 92.8 |
| | | | | | | |
|Recuperación de Pavimento y Carpeta | | 51.00 | 127,225,000.00 | 51.00 | 100.0 | 95.0 |
1 | Loreto-Santa Rosalía | 97.0-109.0 | 12.00 | 39,670,732.00 | 12.00 | 100.0 | 86.0 |
2 | Cd. Insurgentes-Loreto| 52.0-67.0 | 15.00 | 36,338,414.00 | 15.00 | 100.0 | 100.0 |
3 | Cd. Insurgentes-Loreto | 67.0-77.0 | 10.00 | 16,000,000.00 | 10.00 | 100.0 | 100.0 |
4 | La Paz-Cd. Insurgentes | 85.0-99.0 |14.00 | 35,215,854.00 | 14.00 | 100.0 | 97.7 |
| | | | | | | |
| Carpeta | | 2.00 | 3,800,000.00 | 2.00 | 100.0 | 91.7 |
5 | San Pedro-Cabo San Lucas | 46.5-48.5 | 2.00 |3,800,000.00 | 2.00 | 100.0 | 91.7 |
| | | | | | | |
| Renivelación y Riego de Sello | | 41.00 | 49,500,000.00 | 41.00 | 100.0 | 96.7 |
6 | Cabo San Lucas-La Paz | 132.0-152.0 |20.0 | 30,000,000.00 | 20.00 | 100.0 | 100.0 |
7 | Ramal a San Carlos | 48.0-57.0 | 9.0 | 13,500,000.00 | 9.00 | 100.0 | 87.8 |
8 | Loreto - Santa Rosalía | 127.0-139.0 | 12.0 | 6,000,000.00 | 12.00| 100.0 | 100.0 |
| | | | | | | |
| Riego de Sello | | 38.00 | 24,000,000.00 | 38.00 | 100.0 | 79.2 |
9 | Loreto - Santa Rosalía | 65.0-85.0 | 20.0 | 10,000,000.00 | 20.00 |100.0 | 100.0 |
10 | Loreto - Santa Rosalía | | | 5,000,000.00 | | | 0.0 |
11 | Ramal a San Juan de la Costa | 0.0-18.0 | 18.0 | 9,000,000.00 | 18.00 | 100.0 | 100.0 |
| | | ...