FIRE SAFETY PLAN
PROJECT: 2455 MONACO, LAGUNA BEACH
CLIENT: HANNA RESIDENCE
CONTRACTOR: PMR CONSTRUCTION
PROJECT MANAGER: BROCK LYSTER
CONTENTS
1 - Responsibilities2 - Inspections
3 - Portable Fire Extinguishers
4 - Flammable Liquids
5 - Waste Materials
1 - Project Manager Responsibilities
* Ensure and/ or carry out the necessary daily inspections.
* Promote “a fire safe working environment” at all times
* To ensure that all procedures, precautionary measures and safety standards as laiddown in the plan are clearly understood and complied with by all those working on the project.
2 - Inspections
* The project manager shall inspect all portable fire extinguishers, storageareas and waste material on a daily basis.
3 - Portable Fire Extinguishers
* Portable fire extinguishers are located at various points throughout the project, as shown on fire safety site plan.* All persons working on the site must familiarize themselves with the identification, operation, use and location of the fire extinguishers. Trade contractors must ensure that all of theirpersonnel are familiar with the use of portable fire extinguisher.
* Trade contractors employees will be expected to tackle a fire if safe to do so but without putting themselves at risk.
4 -Flammable Liquids
* Flammable liquids and other similar products must be securely stored with an adequate number of suitable fire extinguishers located nearby.
* Only the minimum quantities ofsuch products are to be taken into any building, and are to be removed and securely stored at the end of every working day in secure cages and appropriately signed.
5 - Waste Material
* Wastematerial, if allowed to accumulate, provides an excellent starting point for fire, and good housekeeping is therefore essential. All waste, packing materials, wood, shaving etc must be removed to...