TRABAJOS PRELIMINARES.
TRAZO YLIMPIA.
OPERACIÓN
ES:(15m)(15m)= 225m2
$3.58/m2(225m2)= 805.5
Total: $805.5
CIMENTACION
EXCAVACION A MANO.OPERACIONES:
(1.20m)(1m)= 1.2m3
(1.2m3)(30 zapatas)= 36m3
(36m3)(141.44/m3)= 1,491.84
Total: $1,491.84
PLANTILLA DE CONCRETOOPERACIONES:(1m)(1m)= 1m(1m)(51.48m2)= 51.48m2(51.48m2)(30)=1544.40 Total: $1,544.40 |
ACERO REFUERZO DE CIMENTACION |
OPERACIONES:(12)(0.25)=3(30)(3)=9(9) Total: $216,272.7ALAMBRON EN CIMENTACION |OPERACIONES:(7,485.10)(30)=235,353 Total: $235,353.CIMBRA EN ZAPATAS |
OPERACIONES:(1)(.15)(4)=.6m(.15)(.75)(4)=0.45m0.6+0.45=1.05m2(1.05m2)(30)=31.5m2(31.5m2)(63.80/m2)=2,009.7 Total: $2,009.7CIMBRAEN CONTRATRABES OPERACIONES:(1.20)(1.20)=1.44m(1.44)(30)=43.2m(43.2)(71.19m2)=3,075.408Total: $3,075.408 |
CONCRETO EN CIMENTACION |OPERACIONES:(1)(1)(0.10)=0.1(1)(1)(0.15)=0.15(0.15)(0.15)(0.75)=0.0160.1+0.15+0.75=0.266(0.266)(30)=7.98(7.98)(508.37)=4,056.633Total:$4,056.633CADENA DE CIMENTACION |
Operaciones:(61.5)(73.79)= 4,538.085Total:$4,538.085IMPERMEABILIZACIONCIMENTACION |
Operaciones:(61.5)(7.52/m)=462.48Total=$462.48RELLENO COMPACTADO |
OPERACIONES1.44m3 - 0.266m3=1.17m3(1.17m3)(30)=35.1m3(35.1)(25.62)=899.262Total:$899.262m3ACARREO EN CARRETILLA 20M |
OPERACIONES:(33.07m3)(30)=992.1m3Total:992.1m3 |
TUBO CONCRETO 15 CMOPERACIONES:(.18)(.80)(.90)=0.129(0.129)(57.41)=7.41Total:$7.4 |
|
|REGISTRO 40 X 60 X 1.00 CM |
OPERACIONES:(2)(319.28)= 638.56Total:$638.56TAPA DE REGISTRO |
|
OPERACIONES:(2)(152.89)= 305.78Total:$305.78ESTRUCTURAS:CIMBRA EN COLUMNAS |...