Lot sizing
MRP & ERP
MPS, RCCP, MRP, CRP, & ERP
13-2
MRP & ERP
MANUFACTURING RESOURCE PLANNING
Aggregate Forecast Aggregate Production Plan
Core MRP
Detailed Forecast
Master Production Schedule
Rough-Cut Capacity Planning
Material Requirements Planning
Capacity Requirements Planning
Purchasing
Dispatching
13-3
MRP & ERP
Aggregate Versus DetailedForecasts (Review)
• Use aggregate forecasts for planning medium-range overall production levels.
– High long-range forecast accuracy – Detail not needed for planning long-range resource use (labor, inventory, etc.)
• Use detailed forecasts for initial detailed shortrange Master Production Schedule (MPS)
– Detailed forecasts reasonably accurate for this time frame – Need product-specific detailfor MPS
13-4
MRP & ERP
MPS
13-5
MRP & ERP
From The Aggregate Plan To The MPS
• Suppose that Export TVs, Inc. has the following production plan for the next six months:
Month TVS J F M A M J 12,000 12,000 15,000 15,000 15,000 18,000
• If they make three models, the MPS for January might look like:
MPS 31" 33" 36" 1-Jan 8-Jan 15-Jan 22-Jan 2,000 1,000 0 1,000 1,000 1,000 02,000 0 1,000 3,000 0
13-6
MRP & ERP
Figure 14-4
Planning Horizon
Assembly
Subassembly
Fabrication
Procurement
1
2
3
4
5
6
7
8
9
10
13-7
MRP & ERP
The Master Production Schedule
• An MPS starts with a forecast and a beginning inventory balance
Product X Period Forecast Projected Available Balance Net Requirements MPS Planned OrderRelease Product Y Period Forecast Projected Available Balance Net Requirements MPS Planned Order Release 1 5 20 2 10 3 8 4 5 5 6 6 8
1 7 12
2 2
3 10
4 13
5 5
6 5
13-8
MRP & ERP
The Master Production Schedule
• Inventory is projected forward until a shortage, or “net requirement,” occurs
Product X Period Forecast Projected Available Balance Net Requirements MPS Planned OrderRelease Product Y Period Forecast Projected Available Balance Net Requirements MPS Planned Order Release 1 5 15 2 10 5 3 8 3 4 5 5 6 6 8
20
1 7 12
2 2
3 10
4 13
5 5
6 5
13-9
MRP & ERP
The Master Production Schedule
• Production is scheduled to be completed (the MPS is a planned finish time) to cover the shortfall
Product X Period Forecast Projected AvailableBalance Net Requirements MPS Planned Order Release Product Y Period Forecast Projected Available Balance Net Requirements MPS Planned Order Release 1 5 15 2 10 5 3 8 5 3 8 4 5 5 6 6 8
20
1 7 12
2 2
3 10
4 13
5 5
6 5
13-10
MRP & ERP
The Master Production Schedule
• A planned start time – the “planned order release” is determined based on lead time (here it is one period)Product X Period Forecast Projected Available Balance Net Requirements MPS Planned Order Release Product Y Period Forecast Projected Available Balance Net Requirements MPS Planned Order Release 1 5 15 2 10 5 3 8 5 3 8 4 5 5 6 6 8
20
8
1 7 12
2 2
3 10
4 13
5 5
6 5
13-11
MRP & ERP
The Master Production Schedule
• The process continues until the product isscheduled
Product X Period Forecast Projected Available Balance Net Requirements MPS Planned Order Release Product Y Period Forecast Projected Available Balance Net Requirements MPS Planned Order Release 1 5 15 2 10 5 3 8 5 3 8 4 5 0 5 6 8 6 14 6 8 0
20
8
14
1 7 12
2 2
3 10
4 13
5 5
6 5
13-12
MRP & ERP
The Master Production Schedule
• The other product is scheduledthe same way
Product X Period Forecast Projected Available Balance Net Requirements MPS Planned Order Release Product Y Period Forecast Projected Available Balance Net Requirements MPS Planned Order Release
20
1 5 15
2 10 5
3 8 5 3 8
4 5 0
5 6 8 6 14
6 8 0
8
14
12
1 7 5
2 2 3
3 10 13 7 20
4 13 0
5 5 5 5 10
6 5 0
20
10
13-13
MRP & ERP...
Regístrate para leer el documento completo.