UNIDAD: Ml | | | | | |
MATERIALES | UNIDAD | REND. | DESP. | P. U. | SUB-TOTAL|
Arena | m3 | 0.02 | 7 | 450 | 10.59 |
Grava | m3 | 0.02 | 7 | 450 | 10.59 |
Cemento Gris tipo Portland | Bolsa | 0.39 | 3 | 170 | 68.81 |
Agua de rio | m3 | 0.05 | 25 | 50 | 3.38 |Alambre de Amarre | Lbs | 0.29 | 0 | 39.8 | 11.38 |
Varilla de Hierro Carrugada de 1/4" Lg. | Lance | 0.38 | 5 | 70 | 28.15 |
Varilla de Hierro Carrugada de 3/8" Lg. | Lance | 0.44 | 5 | 165 | 76.23 |Clavos | Lbs | 0.06 | 10 | 25 | 1.51 |
Madera de Pino Para encofrado | P.T. | 1.38 | 3 | 19 | 27.01 |
Sub-Total Materiales | 237.66 |
| | | | | |
MANO DE OBRA | UNIDAD | REND. |DESP. | P. U. | SUB-TOTAL |
CALIFICADA | | | | | |
Albañil | JD | 0.07 | | 300 | 20.10 |
Armador de Hierro | JD | 0.03 | | 269.6 | 8.63 |
Carpintero | JD | 0.15 | | 250 | 37.50|
NO CALIFICADA | | | | | |
Ayudante | JD | 0.07 | | 100 | 6.90 |
Sub-Total M.O | 73.13 |
| | | | | |
EQUIPO | UNIDAD | REND: | DESP. | P. U. | SUB-TOTAL |Herramienta menor | % | 10.00 | | 73.13 | 7.31 |
Sub-Total E. | 7.31 |
COSTO DIRECTO TOTAL: | 318.10 |
Solera superior longitudinal (15x15) cms, de concreto reforzado con 4#3 y anillos #2 @ 20 cms.|
UNIDAD: Ml | | | | | |
MATERIALES | UNIDAD | REND. | DESP. | P. U. | SUB-TOTAL |
Arena | m3 | 0.01 | 7 | 600 | 5.14 |
Grava | m3 | 0.01 | 7 | 600 | 5.14 |
Cemento Gris tipoPortland | Bolsa | 0.22 | 3 | 175 | 39.66 |
Agua de rio | m3 | 0.05 | 25 | 100 | 6.25 |
Alambre de Amarre | Lbs | 0.14 | 0 | 45 | 6.44 |
Varilla de Hierro Carrugada de 1/4" Lg. | Lance | 0.27 | 5| 80 | 22.68 |
Varilla de Hierro Carrugada de 3/8" Lg. | Lance | 0.22 | 5 | 175 | 40.43 |
Clavos | Lbs | 0.04 | 10 | 25 | 0.96 |
Madera de Pino Para encofrado | P.T. | 1.05 | 3 | 45 | 48.62 |...