Hola
1.1 PP Line: Define, Measure and Analysis 06/04/2010 14/04/2010
1.1.1 Develop VSM: Current & Future J. Lavayen/ A. Khare 06/04/2010 07/04/2010
1.1.2 CapacityAnalysys & Simulation J. Lavayen/ A. Khare 09/04/2010 12/04/2010
1.1.3 Materials Flow Analysis A. Almonte/J. Lavayen 13/04/2010 14/04/2010
1.1.4 Place order of Bins in the system J. Marte14/04/2010 14/04/2010
1.2 PP Line: Improvement and Control 22/04/2010 07/05/2010
1.2.1 APQP for PP (Develop FMEA & Control Plan J. Marte/J. Ciprian 22/04/2010 23/04/2010
1.2.2 Update Change in theSystems J. Marte 26/04/2010 30/04/2010
1.2.2.1 Single work order J. Marte/ F. Peguero 26/04/2010 27/04/2010
1.2.2.2 SOPs & other documents J. Marte 28/04/2010 30/04/2010
1.2.3 New layoutimplementation J. Lavayen/J. Marte 01/05/2010 01/05/2010
1.2.4 Place Bins in the Line acording the new Operator Balance Chart J. Marte 03/05/2010 03/05/2010
1.2.5 Communication / Trainning for operators R.Hernandez/J.Lavayen 03/05/2010 03/05/2010
1.2.6 New Flow monitoring J. Marte 03/05/2010 07/05/2010
2 Temno Line Transformation
2.1 Temno Line: Define, Measure and Analysis 04/05/2010 07/05/20102.1.1 Develop Current and Future VSM J. Lavayen / A. Khare/ MT 04/05/2010 05/05/2010
2.1.2 Line balancing, future layout, takt rate, Material Flow J. Lavayen / A. Khare/ MT 05/05/2010 06/05/2010
2.1.3Simulation of the new process flow/ Place W.O. for Bins J. Lavayen / A. Khare/ MT 07/05/2010 07/05/2010
2.2 Temno Line: Improvement and Control 11/05/2010 28/05/2010
2.2.1 APQP for PP (DevelopFMEA & Control Plan P. Taveras 11/05/2010 12/05/2010
2.2.2 Update Change in the Systems P. Taveras 13/05/2010 19/05/2010
2.2.2.1 Single work order P. Taveras 13/05/2010 14/05/2010
2.2.2.2 SOPs &other documents P. Taveras 17/05/2010 19/05/2010
2.2.3 New layout implementation P. Taveras 20/05/2010 20/05/2010
2.2.4 Place Bins in the Line acording the new Operator Balance Chart P. Taveras...